Wednesday, November 26, 2008

Internals

Quickly (because I'm leaving TAFE soon!) a few shots of the insides.


(1) Hot water system in approximately the right place - a lot more to happen yet before it goes though!
(2) Plumbing roughed in. Bath taps are 100mm too low (oh lordy) but apparently that can be fixed. Ah, apprentices.
(3) Scandia Cuisine, has the pipes inside the wood box to hook up to the hot water system. Free hot water from our 25 acres of trees forever!
(4) Gable ends have no wall sarking or cladding yet, and haven't got the external doors on so the weather (OH the weather!) is still getting in. Top priority before we move in 12 days' time is to at least get the place to lockup!!
(5) View of the western gable from inside the ceiling space. We're putting up some sheets of yellow-tongue flooring so that we can use the roof for storage.